Lower-level floor tile lifted before a utility room becomes a dog wash room
Example project
- Home
- 1970s split-level house in Chanhassen with a small tiled utility room on the lower level
- Original request
- Turn the utility room into a dog wash room with a raised tub and a new floor
- Testing
- Tile and mastic tested one at a time: an MDH-certified inspector takes a 9-inch tile piece, then black mastic from beneath it
- Found
- Lab says yes to asbestos in the utility room tile and its mastic
- Area
- About 90 sq ft
- Work
- Tile pried up by hand in whole pieces, the black mastic wetted and scraped
- Timeline
- Five-day notice, then one working day
- Cost
- $2,150
In this example, a family in a 1970s Chanhassen house wants a dog wash room. They plan to turn the small utility room on the lower level into a dog wash room, with a raised tub and a floor that can take water.